Change maximum parallel jobs


By default, the management server starts a maximum of five parallel deployment jobs. In some cases, you may want to increase or reduce this number:

To change maximum parallel jobs

  1. In the console tree, right-click Operations Manager, and then click Configurearrow Server.... The Server Configuration dialog box appears.
  2. Click Namespaces, and then click Policy Management and Deployment. A list of values appears.
  3. Change the value of Number of concurrent deployment threads. The value should be between 5 and 10 in most cases.