Placing all scheduled occurrences of an active job on hold

If an active job is scheduled to run again, you can place the scheduled jobs on hold. The active job continues to run when you place the scheduled occurrences of the active job on hold.

See Scheduled job statuses.

To place all scheduled occurrences of an active job on hold

  1. On the navigation bar, click Job Monitor.

  2. On the Job List tab, in the Current Jobs pane, click the active job that for which you want to hold all scheduled occurrences.

  3. In the task pane, under General Tasks, click Hold Schedule.

    The active job continues and all scheduled occurrences of the job are placed on hold. To remove the hold on future jobs, click Hold Schedule again.

    To select multiple jobs in the Current Jobs pane, select a job, and then press the <Ctrl> or <Shift> keys while you click other jobs that you want to select. This allows you to perform Hold Schedule on more than one job at a time, as long as the state of the jobs are the same.

To remove a scheduled occurrence of an active job from a hold

  1. On the navigation bar, click Job Monitor.

  2. On the Job List tab, in the Current Jobs pane, click the occurence of the job for which you want to remove from a hold.

  3. In the task pane, under General Tasks, clear the Hold Schedule check box by clicking Hold Schedule.

    The active job occurrence is no longer on hold.